Noida DM to homebuyers: Come up with plan to track progress of project
8 years, 5 months ago

Noida DM to homebuyers: Come up with plan to track progress of project

Hindustan Times  

Homebuyers in projects across Noida and Greater Noida who are yet to receive possession of flats in housing complexes met the district magistrate of Gautam Budh Nagar, NP Singh, on Wednesday. Scores of homebuyers, a majority of whom have purchased flats in projects by Amrapali builders, complained about delayed possession, no completion certificate from the authority and a lack of basic amenities at the residential societies that are handed over to the buyers. Indrish Gupta, founder-member of Noida extension flat owners association said, “We have discussed the issue with all the homebuyers in Noida and Greater Noida who went to meet the district magistrate. The schedule of construction of the project will be shared with the government and those who fail to follow the schedule shared with the buyers must be fined,” Jay Prakash, a homebuyer in Amrapali Terrace Homes in Greater Noida west, said.

History of this topic

Build on plot, else lose allotments, Noida warns allottees
6 days, 16 hours ago
Homebuyers Can't Suffer Due To NOIDA Authority's Failure To Fully Implement Project: Allahabad HC On Withholding Of Occupancy Certificate
3 weeks, 5 days ago
Greater Noida authority to hold demolition drive in Chhapraula
2 months ago
Greater Noida authority files FIRs against 18 builders for illegal construction
2 months, 3 weeks ago
Noida hires private agency to help acquire plots for land bank
3 months ago
Noida authority seals 27 flats of Skytech Matrott over financial dues
3 months ago
Noida sets aside ₹60 crore to improve civic amenities in urban villages
3 months, 1 week ago
NGT orders immediate halt on illegal constructions in Noida, Greater Noida
3 months, 1 week ago
Noida building projects without clearances not to proceed with construction: NGT
Trending News
3 months, 1 week ago
Allahabad HC notice to Greater Noida authority over Abadi land
3 months, 2 weeks ago
Noida: Realtors asked to execute registry to homebuyers by Dec 31
3 months, 2 weeks ago
Greater Noida: UP govt forms new committee to look into farmer demands
3 months, 3 weeks ago
Noida authority seeks EOW probe against reality project
3 months, 3 weeks ago
Greater Noida body warns builders to initiate flat registry in 15 days
6 months, 2 weeks ago
NCR real estate news: Developers demand more time, waivers to complete stuck housing projects
6 months, 3 weeks ago
Good news for homebuyers! Noida authority approves maps of Unitech’s stuck housing projects
8 months, 3 weeks ago
Yeida to prepare new guidelines for land allotment after M3M dispute
9 months, 2 weeks ago
Noida authority to act against 12 realtors for not paying dues
10 months ago
Noida: Three-member committee soon to soon submit report on farmers’ demands
10 months, 1 week ago
Greater Noida authority holds talks with builders on homebuyer registry
10 months, 2 weeks ago
UP govt asks Noida, Greater Noida to cancel allotments of realtors who still have land dues
10 months, 2 weeks ago
78 home-buyers in Noida Sec 107 get flat registry
10 months, 3 weeks ago
Noida: Proposal for homeowners to pay more for registering flats mooted
10 months, 3 weeks ago
Residents of Noida high-rise to take out ‘march for registry’
11 months, 1 week ago
Noida and Greater Noida flat registries: 5 things homebuyers should know
11 months, 3 weeks ago
Noida authority allows registration of 13,639 apartments
11 months, 3 weeks ago
Legacy stalled projects: 1,366 home registries done in March in Greater Noida
11 months, 3 weeks ago
Greater Noida homebuyers protest over seven-year delay in handing over apartments
1 year ago
Yeida to issue registry permission for 10k apartments
1 year ago
Builders agree to pay dues, Noida authority gives nod to process registries of 13,600 flats
1 year ago
7 things you need to know about Greater Noida Authority’s group housing plot scheme
1 year, 1 month ago
Noida to give nod for execution of registries of 3,000 flats in 31 unfinished projects
1 year, 2 months ago
Greater Noida authority holds meeting with realtors
1 year, 2 months ago
Over 3,000 flats registered in 3 months in Greater Noida, 6,000 expected by Diwali
1 year, 5 months ago
Noida Authority CEO meets builders over ₹26,000 crore pending dues
1 year, 7 months ago
Central committee proposes several measures to provide relief to homebuyers in UP. Know all suggestions here
1 year, 7 months ago
Homebuyers in Greater Noida protest against developer for delay in project delivery
1 year, 9 months ago
Uttar Pradesh: Comprehensive action plan in 2 weeks to resolve stuck up Noida housing projects
1 year, 10 months ago
Noida, Greater Noida builders seek one-time settlement scheme for land dues | KNOW DETAILS
2 years, 3 months ago
Noida land rate: All you need to know about latest revisions
2 years, 7 months ago
NOIDA Authority's Demolition Drive Along Yamuna Floodplains Temporarily Halted By Allahabad High Court
2 years, 9 months ago
Greater Noida Authority demolishes 8 shops, 4 flats illegally built in Shahberi
2 years, 10 months ago
NCR homebuyers, awaiting possession papers for years, ask UP govt to intervene
3 years, 8 months ago
Noida Authority to Unitech: Pay ₹2,734 crore dues in 15 days or lose land
5 years, 6 months ago
Good news for Amrapali homebuyers: SC orders Noida, Greater Noida authorities to begin flat registration immediately or face jail
5 years, 7 months ago
Noida authority to issue occupancy papers for ready flats in Amrapali projects
5 years, 8 months ago
Amrapali buyers worry Greater Noida authority won’t finish 35,000 flats
5 years, 10 months ago
Noida: Buyers protest non-delivery of Amrapali flats
6 years, 4 months ago
Ensure Noida does not turn into a shanty town, says MP Sharma
7 years ago
Yogi govt cracks whip on errant developers, orders arrest of 8 Noida builders for failing to deliver flats
7 years, 3 months ago

Discover Related