WB REAT Facilitates Settlement Between Builder And Homebuyer Over Termination Of Flat Booking Due To Non-Payment Of Total Consideration
3 months, 3 weeks ago

WB REAT Facilitates Settlement Between Builder And Homebuyer Over Termination Of Flat Booking Due To Non-Payment Of Total Consideration

Live Law  

West Bengal Real Estate Appellate Tribunal bench, comprising Justice Rabindranath Samanta and Dr. Subrat Mukherjee, oversaw and facilitated a settlement between a builder and a homebuyer. Background Facts The Homebuyer booked a flat in the builder's project named ONE 10 situated at Mouza — Thakdari under Bidhannagar Municipal Corporation, North 24 Parganas. Observation and Direction by Authority During the pendency of the matter, the Tribunal directed both the homebuyer and the builder to enter into a settlement agreement on July 30, 2024. Finally the Tribunal disposed of the appeal after noting that the homebuyer had paid the amount as directed and the builder had executed and registered the deed of conveyance in favor of the homebuyer.

History of this topic

Delhi REAT Holds Homebuyer Who Booked Flat Under Buy-Back Scheme As Allottee, Remands Matter To Delhi RERA
1 month, 2 weeks ago
Telangana RERA Penalises Builder For Unilaterally Cancelling Homebuyers Allotment, Also Holds Real Estate Agent Liable
1 month, 2 weeks ago
West Bengal REAT Restrains Yes Bank From Taking Possession Of Flats And Selling Them At Auction To Recover Loan Provided To Builder
1 month, 3 weeks ago
WBREAT Directs Builder To Pay Interest To Homebuyer For Delayed Possession And Hand Over Flat With Car Parking Space
2 months, 1 week ago
WBREAT Directs Builder To Hand Over Possession Of Flat To Homebuyer And Pay Interest For Delay
2 months, 1 week ago
Homebuyer Forced To Vacate Flat After Taking Possession Due To Unsafe Construction, Haryana RERA Directs NBCC To Pay Compensation
2 months, 2 weeks ago
Real Estate Monthly Digest : December 2024
Trending News
2 months, 3 weeks ago
Real Estate Weekly Round Up:[16 th December – 22 nd December 2024]
2 months, 3 weeks ago
Karnataka RERA Orders Dharwad-Based Builder To Refund ₹38.8 Lakhs To Homebuyer Due To Delay
3 months, 1 week ago
REAL ESTATE WEEKLY ROUND UP: DECEMBER 2 – DECEMBER 8
3 months, 1 week ago
RERA WEEKLY ROUND UP NOVEMBER 11 – NOVEMBER 17
3 months, 3 weeks ago
WBREAT Upholds Decision To Refund Complainant Who Booked Two Plots In Mini Township Project By Advance Payment In 2014
Trending News
4 months ago
WBREAT Upholds Order Directing Builder To Pay Over ₹56 Lakh Over Failure To Provide Possession Of Four Plots By November 2016
4 months ago
WB REAT Upholds Authority's Decision Directing Builder To Refund ₹11 Lakh To Homebuyer, Initiates Proceedings For Selling Unregistered Project
4 months, 2 weeks ago
WB REAT Directs Builder To Pay Settlement Of Over ₹2 Crores To Homebuyer For Failure To Deliver Possession Since 2017
4 months, 2 weeks ago
Delay Of 4 Years In Offering Possession, Punjab RERA Orders Builder To Pay Compensation To Homebuyer For Mental Agony
8 months ago
Builder Failed To Commence Construction Even After Two Years From Agreement Date, Karnataka RERA Orders Refund To Homebuyer
9 months ago
Haryana RERA Upholds Builder's Termination Of Flat Booking After Homebuyer Failed To Make Timely Payments
9 months, 1 week ago
RERA Weekly Round Up – 27 May To 2 June 2024
9 months, 2 weeks ago
Homebuyer Paid Booking Price On Spot Without Reading Terms Of Document, Karnataka RERA Orders Full Refund
11 months, 2 weeks ago
MahaRERA cancels home buyers’ agreement
11 months, 3 weeks ago

Discover Related