
Prolongation Compensation Can't Be Granted If The Contractor Didn't Reserve Claim For Compensation At The Time Of The EOT: Delhi High Court
Live LawThe Delhi High Court has held that no compensation can be awarded for the prolongation of the contract if the contractor did not reserve its right to such compensation at the time of the seeking Extension of Time. They ruled that the Tribunal's decision, which denied the prolongation cost due to the Contractor's failure to reserve this right during the EOT request, and because the EOT was granted without financial implications, is a plausible view which does not warrant intervention by the Court using its powers under Section 34 of the A&C Act. Aggrieved by this finding, the petitioner challenged the award under Section 34 of the A&C Act Grounds of Challenge The petitioner challenged the award on the following grounds: The finding of the arbitral tribunal suffers from the vice of patent illegality inasmuch as, the tribunal while limiting the compensation to six months, returned a perverse finding that in seeking EOT on the first, second and fourth occasion, the Contractor had not reserved its right to seek compensation, which amounted to a waiver. The Court held that the tribunal did not disallow the claims on the grounds of any prohibition in the contract but due to petitioner’s own waiver of the right to claim compensation, that happened in the first, second and fourth EOT sought by it.
History of this topic

Arbitrator Failed To Deal With Material Contentions, Arbitral Award Would Not Satisfy The Requirement Of A Reasoned Award: Delhi High Court
Live Law
Mere Delay By Employer Would Not Entitle The Contractor To Damages Unless The Loss Is Pleaded And Proved: Delhi High Court
Live Law
Arbitral Tribunal Can Award Damages For Delay Attributable To Employer Even When The Agreement Provides For The Extension Of Time As The Only Remedy To The Contractor: Delhi High Court
Live Law
Arbitral Tribunal Can Award Damages For Delay By Employer Even In Absence Of Any Clause In Agreement : Delhi High Court
Live Law
Claim Of Damages, Supplementary Agreement Executed Under Duress Can’t Come In The Way : Delhi High Court
Live Law
Liquidated Damages Can't Be Imposed When The Engineer-In-Charge Holds That The Cause Of Delay Is Explained: Delhi High Court
Live Law![Payment To Contractors Shouldn't Be Delayed For Non-Availability Of Funds Once Work Is Done: Delhi HC to Civic bodies; Issues Guidelines [Read Judgment]](/static/images/error.jpg)
Payment To Contractors Shouldn't Be Delayed For Non-Availability Of Funds Once Work Is Done: Delhi HC to Civic bodies; Issues Guidelines [Read Judgment]
Live LawDiscover Related











![[Arbitration Act] Limitation Does Not Stop If Initial Filing Is Non Est, Date Of Filing Must Be Reckoned From Date Of Refiling: Delhi HC](/static/images/error.jpg)









![[Arbitration Act] Referral Courts Can't Indulge In Enquiry Into Whether Claims Are Time-Barred: Calcutta High Court](/static/images/error.jpg)





![IBC Weekly Round-Up [2nd February-9th February 2025]](/static/images/error.jpg)




















