WBREAT Upholds Order Directing Builder To Pay Over ₹56 Lakh Over Failure To Provide Possession Of Four Plots By November 2016
4 months, 1 week ago

WBREAT Upholds Order Directing Builder To Pay Over ₹56 Lakh Over Failure To Provide Possession Of Four Plots By November 2016

Live Law  

West Bengal Real Estate Appellate Tribunal bench comprising Justice Rabindranath Samanta, Gour Sunder Banerjee and Dr. Subrat Mukherjee has provided relief to the complainant who purchased four plots by paying advance money in the builder's mini township project and was expecting possession by November 2016. The Tribunal upheld the Authority's order directing the builder to refund the principal amount of Rs. Authority through its order dated 21.06.23 directed builder to refund the amount paid by complainant with interest. Therefore, the Tribunal dismissed the builder's appeal with costs and upheld the authority's order dated 21.06.2023 directing builder to refund the principal amount of Rs.

History of this topic

WBREAT Directs Builder To Pay Interest To Homebuyer For Delayed Possession And Hand Over Flat With Car Parking Space
2 months, 2 weeks ago
WBREAT Directs Builder To Hand Over Possession Of Flat To Homebuyer And Pay Interest For Delay
2 months, 2 weeks ago
Real Estate Weekly Round Up:[16 th December – 22 nd December 2024]
3 months ago
Karnataka RERA Orders Dharwad-Based Builder To Refund ₹38.8 Lakhs To Homebuyer Due To Delay
3 months, 2 weeks ago
REAL ESTATE WEEKLY ROUND UP: DECEMBER 2 – DECEMBER 8
3 months, 2 weeks ago
RERA WEEKLY ROUND UP NOVEMBER 11 – NOVEMBER 17
4 months ago
WB REAT Facilitates Settlement Between Builder And Homebuyer Over Termination Of Flat Booking Due To Non-Payment Of Total Consideration
4 months, 1 week ago
WBREAT Upholds Decision To Refund Complainant Who Booked Two Plots In Mini Township Project By Advance Payment In 2014
Trending News
4 months, 1 week ago
Delay Of 3.5 Years In Delivering Possession Of Plot, Himachal RERA Directs Builder To Pay Rs. 2.92 Crore As Interest To Complainant
4 months, 2 weeks ago
WB REAT Upholds Authority's Decision Directing Builder To Refund ₹11 Lakh To Homebuyer, Initiates Proceedings For Selling Unregistered Project
4 months, 3 weeks ago
WB REAT Directs Builder To Pay Settlement Of Over ₹2 Crores To Homebuyer For Failure To Deliver Possession Since 2017
4 months, 3 weeks ago
Refund Offer From Builder After Long Delay Considered Inadequate: NCDRC
6 months, 3 weeks ago
Buyers Have Rights To Refund In Cases Of Delay And Cancellation Of Allotment: NCDRC
7 months, 2 weeks ago
MahaRERA - Homebuyers Accepting Partial Refund From Builder Without Interest Can't Later Seek Refund With Interest
8 months ago
Delay Of 4 Years In Offering Possession, Punjab RERA Orders Builder To Pay Compensation To Homebuyer For Mental Agony
8 months, 1 week ago
MahaRERA Orders Jayesh Buildcon To Pay Interest To Homebuyers For Delay In Handing Over Possession
8 months, 2 weeks ago
Builder Failed To Commence Construction Even After Two Years From Agreement Date, Karnataka RERA Orders Refund To Homebuyer
9 months, 1 week ago
HPRERA - Builder Cannot Demand Full Payment from Homebuyer If Project's Occupancy Certificate Has Not Been Obtained
11 months, 2 weeks ago
Haryana RERA Directs Builder To Refund The Homebuyer's Amount With Interest, Rejects Builder's Investor Argument
11 months, 3 weeks ago
Builder ordered to pay Rs 1 lakh for delaying flat possession