Mere Delay By Employer Would Not Entitle The Contractor To Damages Unless The Loss Is Pleaded And Proved: Delhi High Court
1 year ago

Mere Delay By Employer Would Not Entitle The Contractor To Damages Unless The Loss Is Pleaded And Proved: Delhi High Court

Live Law  

The High Court of Delhi has held that merely because the delay in the execution of the work is attributable to the employer, the same would not entitle the contractor to claim damages unless it pleads and proves that such delay resulted in loss to it. The bench of Justices Vibhu Bakhru and Tara Vitasta Ganju held that a procedural order passed by the earlier arbitrator, not being a final decision on the merits, does not preclude the substitute arbitrator from deciding the claims on their merits. However, the arbitrator was substituted under Section 29A and the substituted arbitrator continued the arbitral proceedings and dismissed majority of appellant's claims on ground of failure to plead and prove loss of profit. Contention of the Parties The appellant challenged the award on the following grounds: That the impugned award is contrary to an earlier order by the First Arbitrator on the issue of cause of action wherein the arbitrator has expressly observed that there is sufficient cause of action for the appellant's claims. The Court that observations made in a procedural order passed by the earlier arbitrator, not being a final decision on the merits, does not preclude the substitute arbitrator from deciding the claims on their merits.

History of this topic

Delhi High Court Sets Aside Claim Of Rs.15 Lakh Awarded By Arbitral Tribunal Due To Lack Of Evidence
3 months, 2 weeks ago
Delhi High Court Sets Aside Claim Of Rs.15 Lakh Awarded By Arbitral Tribunal Due To Lack Of Evidence
3 months, 2 weeks ago
Award Cannot Be Set Aside U/S 34 Of Arbitration Act If View Taken By Arbitrator Is A Plausible View: Delhi High Court
4 months, 2 weeks ago
Arbitral Tribunal Can Award Compensation For Breach If Contract Is Incapable Of Specific Performance: Delhi High Court
8 months, 1 week ago
Take Steps To Avoid Delays In Filing Arbitration Appeals: Allahabad High Court To State's Principal Law Secretary
8 months, 3 weeks ago
Arbitrator Failed To Deal With Material Contentions, Arbitral Award Would Not Satisfy The Requirement Of A Reasoned Award: Delhi High Court
11 months ago
Arbitral Tribunal Can Award Damages For Delay Attributable To Employer Even When The Agreement Provides For The Extension Of Time As The Only Remedy To The Contractor: Delhi High Court
1 year, 2 months ago
Arbitral Tribunal Can Award Damages For Delay By Employer Even In Absence Of Any Clause In Agreement : Delhi High Court
1 year, 2 months ago
Arbitrator Failed To Consider Document Based On Procedural Defects, Delhi High Court Sets Aside Award
1 year, 5 months ago
Prolongation Compensation Can't Be Granted If The Contractor Didn't Reserve Claim For Compensation At The Time Of The EOT: Delhi High Court
1 year, 5 months ago
Award On Damages Cannot Be Sustained Just On Penalty Clause In Agreement: Delhi High Court
1 year, 5 months ago
Delay In The Handing Over The Work Front Affecting Completion Is A Material Breach : Delhi High Court
1 year, 5 months ago
Delay In Approaching Appointing Authority For Constitution Of Tribunal, Won’t Render Claims Time Barred: Delhi High Court
2 years, 1 month ago
Employer Cannot Retain Performance Bank Guarantee After Acknowledging Of Due Performance: Delhi High Court
2 years, 3 months ago
Circumstances Mentioned Under Schedules V Do Not Per Se Render The Arbitrator Ineligible: Delhi High Court
2 years, 4 months ago
Liquidated Damages Can't Be Imposed When The Engineer-In-Charge Holds That The Cause Of Delay Is Explained: Delhi High Court
2 years, 10 months ago
Inordinate And Unexplained Delay In Rendering Arbitral Award Is Against Public Policy Of India: Delhi High Court
2 years, 10 months ago
'Impedes Access To Information': High Court Directs Delhi Labour Dept To Ensure Uploading Of Orders Passed By Employee Compensation Commissioners
3 years, 6 months ago
Payment To Contractors Shouldn't Be Delayed For Non-Availability Of Funds Once Work Is Done: Delhi HC to Civic bodies; Issues Guidelines [Read Judgment]
7 years ago
Proof Of Injury Suffered Necessary For Awarding Damages Towards Loss Of Profits In Arbitration Proceedings: Delhi HC [Read Judgment]
7 years, 5 months ago
Delhi HC Frowns Upon Rampant Practice Of Litigants Blaming Their Lawyers [Read Judgment]
7 years, 6 months ago
Delhi HC Frowns Upon Rampant Practice Of Litigants Blaming Their Lawyers [Read Judgment]
7 years, 6 months ago

Discover Related